DESIGN BUILD CONSTRUCTION SERVICES TO RENOVATE AND UPGRADE THE HILL AIR FORCE BASE BUILDING 1286 STEAM PLANT.
Awardee
Place of Performance
Highland, UT 84003 United States
Pricing
Fixed Price
Set Aside
Small Business Set Aside - Total (SBA)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 03/20/24 to 04/15/25 and the Potential Award value has increased from $21,736,639 to $21,898,574.
NH1 JV was awarded Definitive Contract W9123822C0023 (W91238-22-C-0023) for Design Build Construction Services To Renovate And Upgrade The Hill Air Force Base Building 1286 Steam Plant. worth up to $21,898,574 by USACE Sacramento District in September 2022. The contract has a duration of 2 years 7 months and was awarded through solicitation USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT with a Small Business Total set aside with NAICS 236220 and PSC Z2NB via two step acquisition procedures with 3 bids received. As of today, the Definitive Contract has a total reported backlog of $161,935 and funded backlog of $161,935.

DOD Announcements

Sep 2022: NH1 JV,* Highland, Utah, was awarded a $21,736,639 firm-fixed-price contract to replace existing boilers with new dual-fuel boilers. Bids were solicited via the internet with three received. Work will be performed in Hill Air Force Base, Utah, with an estimated completion date of March 24, 2025. Fiscal 2022 operation and maintenance, Air Force funds in the amount of $21,736,639 were obligated at the time of the award. U.S. Army Corps of Engineers, Sacramento, California, is the contracting activity (W91238-22-C-0023).

Status
(Open)

Last Modified 12/20/23
Period of Performance
9/22/22
Start Date
4/15/25
Current End Date
4/15/25
Potential End Date
59.0% Complete

Obligations and Backlog
$21.7M
Total Obligated
$21.9M
Current Award
$21.9M
Potential Award
99% Funded
$161.9K
Funded Backlog
$161.9K
Total Backlog

Award Hierarchy

Definitive Contract

W9123822C0023

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W9123822C0023

Opportunity Lifecycle

Procurement history for W9123822C0023

Transaction History

Modifications to W9123822C0023

People

Suggested agency contacts for W9123822C0023

Competition

Number of Bidders
3
Solicitation Procedures
Two Step
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
NS7TRNRTKWG4
Awardee CAGE
948U3
Agency Detail
Awarding Office
W91238 W075 ENDIST SACRAMENTO
Funding Office
W91238
Created By
christopher.s.paxman@usace.army.mil
Last Modified By
christopher.s.paxman@usace.army.mil
Approved By
christopher.s.paxman@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
UT-03
Senators
Mike Lee
Mitt Romney
Representative
John Curtis

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Military Construction, Army (021-2050) Department of Defense-Military Land and structures (32.0) $21,736,639 100%
Modified: 12/20/23