CONSTRUCTION OF THE NEW THIRD LOCK, NEW LOCK AT THE SOO, SAULT STE. MARIE, MICHIGAN.
Place of Performance
Sault Sainte Marie, MI 49783 United States
Pricing
Fixed Price With Economic Price Adjustment
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Infrastructure $721,454,350 (40%) percent this Definitive Contract was funded by the 2021 Infrastructure Act.
Amendment Since initial award the Potential End Date has been extended from 07/30/27 to 07/08/29 and the Potential Award value has increased from $1,888,341,380 to $1,888,531,094.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Kokosing Alberici Traylor was awarded Definitive Contract W911XK22C0006 (W911XK-22-C-0006) for Construction Of The New Third Lock, New Lock At The Soo, Sault Ste. Marie, Michigan. worth up to $1,888,531,094 by USACE Detroit District in June 2022. The contract has a duration of 7 years 1 months and was awarded through solicitation New Lock at the Soo, New Third Lock full & open with NAICS 237990 and PSC Y1KA via direct negotiation acquisition procedures with 2 bids received. As of today, the Definitive Contract has a total reported backlog of $93,589,714 and funded backlog of $189,714.

DOD Announcements

Jul 2022: Kokosing Alberici Traylor LLC, Westerville, Ohio, was awarded a $1,068,052,150 fixed-price-with-EPA contract to construct the lock chamber of the New Soo Lock at Sault Sainte Marie, Michigan. Bids were solicited via the internet with two received. Work will be performed in Sault Sainte Marie, Michigan, with an estimated completion date of July 26, 2029. Fiscal 2022 civil construction funds in the amount of $1,068,052,150 were obligated at the time of the award. U.S. Army Corps of Engineers, Detroit, Michigan, is the contracting activity (W911XK-22-C-0006).

Status
(Open)

Last Modified 4/24/25
Period of Performance
6/30/22
Start Date
7/8/29
Current End Date
7/8/29
Potential End Date
42.0% Complete

Obligations and Backlog
$1.8B
Total Obligated
$1.8B
Current Award
$1.9B
Potential Award
95% Funded
$189.7K
Funded Backlog
$93.6M
Total Backlog

Award Hierarchy

Definitive Contract

W911XK22C0006

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to W911XK22C0006

Opportunity Lifecycle

Procurement history for W911XK22C0006

Transaction History

Modifications to W911XK22C0006

People

Suggested agency contacts for W911XK22C0006

Competition

Number of Bidders
2
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Yes
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
Construction
IT Commercial Item Category
Not Applicable
Awardee UEI
JKR3GLXEDRD1
Awardee CAGE
914G9
Agency Detail
Awarding Office
W911XK W072 ENDIST DETROIT
Funding Office
W911XK
Created By
darin.w.larson@usace.army.mil
Last Modified By
keith.e.frentz.civ.lrd@sc.sa
Approved By
darin.w.larson@usace.army.mil

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
MI-01
Senators
Debbie Stabenow
Gary Peters
Representative
Jack Bergman

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Construction, Corps of Engineers - Civil (096-3122) Water resources Land and structures (32.0) $1,329,761,500 99%