N0002413C2305
Definitive Contract
Overview
Government Description
FY13-FY17 DDG 51 CLASS SHIP CONSTRUCTION.
Alternate Description
DDG 51
Awardee
Funding Agency
Place of Performance
Bath, ME 4530 United States
Pricing
Fixed Price Incentive
Set Aside
None
Extent Competed
Full And Open Competition After Exclusion Of Sources
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 07/31/23 to 12/01/26 and the Potential Award value has increased 12% from $4,457,302,964 to $5,007,028,583.
Subcontracting Plan This Definitive Contract has a Subcontracting Plan (without incentive). The Department of Defense has an overall small business subcontracting goal of 30%
Subcontracting Plan This Definitive Contract has a Subcontracting Plan (without incentive). The Department of Defense has an overall small business subcontracting goal of 30%
Bath Iron Works Corporation was awarded
Definitive Contract N0002413C2305 (N00024-13-C-2305)
for Fy13-Fy17 Ddg 51 Class Ship Construction.
worth up to $5,007,028,583
by Naval Sea Systems Command
in June 2013.
The contract
has a duration of 13 years 6 months and
was awarded
through solicitation FY 13-17 USS ARLEIGH BURKE (DDG 51) Class Guided Missile Destroyers Construction
full & open
with
NAICS 336611 and
PSC 1905
via direct negotiation acquisition procedures with 2 bids received.
As of today, the Definitive Contract has a total reported backlog of $193,316,731 and funded backlog of $177,409,314.
DOD Announcements
Jun 2017:
General Dynamics Bath Iron Works, Bath, Maine, is being awarded a $9,671,294 cost-plus-fixed-fee order against a previously awarded contract (N00024-13-C-2305) to provide procurement and management efforts in support of the land-based engineering site shore based spares. This order is to procure three 4160 switchboards with two load centers, three 4160 transformers, three high resistance grounding assemblies, and two cooling fans. Work will be performed in Philadelphia, Pennsylvania, and is expected to be completed by December 2018. Fiscal 2016 shipbuilding and conversion (Navy) funds in the amount of $9,671,294 will be obligated at time of award and will not expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity.
Sep 2017: General Dynamics Bath Iron Works, Bath, Maine, is being awarded a fixed-price-incentive-firm target modification to a previously awarded contract (N00024-13-C-2305) for incorporation of the Flight III baseline on DDG 126 and award of one fiscal 2016 ship (DDG 127) in the Flight IIA configuration. Flight III will incorporate the SPY-6 Air and Missile Defense Radar (AMDR) and upgrade the electrical power and cooling capacity plus additional associated changes. The fiscal 2016 ship was appropriated by Congress in the 2016 Consolidated Appropriations Act (P.L. 114-113). As the Navy expects to release a competitive solicitation for additional DDG 51 class ships in the Flight III configuration in future years, the contract award amount is considered source selection sensitive information (see 41 U.S. Code 2101, et seq., Federal Acquisition Regulation (FAR) 2.101 and FAR 3.104) and will not be made public at this time. Work for DDG 126 and 127 will be performed in Bath, Maine (62 percent); Walpole, Massachusetts (5 percent); Cincinnati, Ohio (5 percent); Coatesville, Pennsylvania (2 percent); York, Pennsylvania (2 percent); South Portland, Maine (1 percent); Falls Church, Virginia (1 percent); and other locations below 1 percent (collectively totaling 22 percent), and is scheduled to complete in fiscal 2024. Fiscal 2016 shipbuilding and conversion (Navy); and fiscal 2017 shipbuilding and conversion (Navy) funding will be obligated at time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, District of Columbia, is the contracting activity.
Jun 2021: Bath Iron Works, Bath, Maine, was awarded an $8,683,913 fixed-price incentive, firm target modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post- delivery availability work items for DDG 120. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by July 2022. Fiscal 2013 shipbuilding and conversion (Navy) funding in the amount of $6,440,409 will be obligated at time of award and will not expire at the end of the current fiscal year. Fiscal 2020 other procurement (Navy) funding in the amount of $2,243,962 will also be obligated at time of award and will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion and Repair, Bath, Maine, is the contracting activity. (Awarded June 21, 2021)
Mar 2023: Bath Iron Works, Bath, Maine, is awarded a $9,609,633 fixed-price incentive (firm target) modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post-delivery availability work items for DDG 122. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by January 2024. Fiscal 2015 shipbuilding and conversion (Navy) funding in the amount of $7,749,330 (81%); and fiscal 2021 other procurement (Navy) funding in the amount of $1,860,303 (19%) will be obligated at time of award, of which $1,860,303 will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity (N00024-13-C-2305).
Mar 2023: Bath Iron Works, Bath, Maine, is awarded a $9,609,633 fixed-price incentive (firm target) modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post-delivery availability work items for DDG 122. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by January 2024. Fiscal 2015 shipbuilding and conversion (Navy) funding in the amount of $7,749,330 (81%); and fiscal 2021 other procurement (Navy) funding in the amount of $1,860,303 (19%) will be obligated at time of award, of which $1,860,303 will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity (N00024-13-C-2305).
Aug 2024: Bath Iron Works, Bath, Maine, is awarded a $7,802,168 fixed-price incentive (firm target) modification to previously awarded contract (N00024-13-C-2305) to accomplishment of post-delivery availability work items for DDG 124. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations collectively will be below 1%, and is expected to be completed by July 2025. Fiscal 2016 shipbuilding and conversion (Navy) funding in the amount of $7,802,168 will be obligated at time of award and will not expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity.
Sep 2017: General Dynamics Bath Iron Works, Bath, Maine, is being awarded a fixed-price-incentive-firm target modification to a previously awarded contract (N00024-13-C-2305) for incorporation of the Flight III baseline on DDG 126 and award of one fiscal 2016 ship (DDG 127) in the Flight IIA configuration. Flight III will incorporate the SPY-6 Air and Missile Defense Radar (AMDR) and upgrade the electrical power and cooling capacity plus additional associated changes. The fiscal 2016 ship was appropriated by Congress in the 2016 Consolidated Appropriations Act (P.L. 114-113). As the Navy expects to release a competitive solicitation for additional DDG 51 class ships in the Flight III configuration in future years, the contract award amount is considered source selection sensitive information (see 41 U.S. Code 2101, et seq., Federal Acquisition Regulation (FAR) 2.101 and FAR 3.104) and will not be made public at this time. Work for DDG 126 and 127 will be performed in Bath, Maine (62 percent); Walpole, Massachusetts (5 percent); Cincinnati, Ohio (5 percent); Coatesville, Pennsylvania (2 percent); York, Pennsylvania (2 percent); South Portland, Maine (1 percent); Falls Church, Virginia (1 percent); and other locations below 1 percent (collectively totaling 22 percent), and is scheduled to complete in fiscal 2024. Fiscal 2016 shipbuilding and conversion (Navy); and fiscal 2017 shipbuilding and conversion (Navy) funding will be obligated at time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, District of Columbia, is the contracting activity.
Jun 2021: Bath Iron Works, Bath, Maine, was awarded an $8,683,913 fixed-price incentive, firm target modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post- delivery availability work items for DDG 120. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by July 2022. Fiscal 2013 shipbuilding and conversion (Navy) funding in the amount of $6,440,409 will be obligated at time of award and will not expire at the end of the current fiscal year. Fiscal 2020 other procurement (Navy) funding in the amount of $2,243,962 will also be obligated at time of award and will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion and Repair, Bath, Maine, is the contracting activity. (Awarded June 21, 2021)
Mar 2023: Bath Iron Works, Bath, Maine, is awarded a $9,609,633 fixed-price incentive (firm target) modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post-delivery availability work items for DDG 122. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by January 2024. Fiscal 2015 shipbuilding and conversion (Navy) funding in the amount of $7,749,330 (81%); and fiscal 2021 other procurement (Navy) funding in the amount of $1,860,303 (19%) will be obligated at time of award, of which $1,860,303 will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity (N00024-13-C-2305).
Mar 2023: Bath Iron Works, Bath, Maine, is awarded a $9,609,633 fixed-price incentive (firm target) modification to previously awarded contract N00024-13-C-2305 to exercise an option for accomplishment of post-delivery availability work items for DDG 122. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations below 1% (collectively totaling less than 1%), and is expected to be completed by January 2024. Fiscal 2015 shipbuilding and conversion (Navy) funding in the amount of $7,749,330 (81%); and fiscal 2021 other procurement (Navy) funding in the amount of $1,860,303 (19%) will be obligated at time of award, of which $1,860,303 will expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity (N00024-13-C-2305).
Aug 2024: Bath Iron Works, Bath, Maine, is awarded a $7,802,168 fixed-price incentive (firm target) modification to previously awarded contract (N00024-13-C-2305) to accomplishment of post-delivery availability work items for DDG 124. Work will be performed in Bath, Maine (93%); Brunswick, Maine (6%); and other locations collectively will be below 1%, and is expected to be completed by July 2025. Fiscal 2016 shipbuilding and conversion (Navy) funding in the amount of $7,802,168 will be obligated at time of award and will not expire at the end of the current fiscal year. The Supervisor of Shipbuilding, Conversion, and Repair, Bath, Maine, is the contracting activity.
Status
(Open)
Last Modified 4/23/25
Period of Performance
6/3/13
Start Date
12/1/26
Current End Date
12/1/26
Potential End Date
Obligations and Backlog
$4.8B
Total Obligated
$5.0B
Current Award
$5.0B
Potential Award
$177.4M
Funded Backlog
$193.3M
Total Backlog
Award Hierarchy
Definitive Contract
N0002413C2305
Subcontracts
Activity Timeline
Subcontract Awards
Disclosed subcontracts for N0002413C2305
Opportunity Lifecycle
Procurement history for N0002413C2305
Transaction History
Modifications to N0002413C2305
People
Suggested agency contacts for N0002413C2305
Competition
Number of Bidders
2
Solicitation Procedures
Negotiated Proposal/Quote
Other Than Full and Open Competition
Mobilization, Essential R&D
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Plan Required (Incentive Not Included)
Cost Accounting Standards
Yes
Business Size Determination
Large Business
Defense Program
DoD Claimant Code
Ships
IT Commercial Item Category
Not Applicable
Awardee UEI
FREEMCLKFXE3
Awardee CAGE
70876
Agency Detail
Awarding Office
N62786 SUP OF SHIPBUILDING CONV AND REPAIR
Funding Office
N00024
Created By
morgan.whitney.n62786@supshipba.navy.mil
Last Modified By
morgan.whitney.n62786@supshipba.navy.mil
Approved By
morgan.whitney.n62786@supshipba.navy.mil
Legislative
Legislative Mandates
Materials, Supplies, Articles & Equipment
Performance District
ME-01
Senators
Susan Collins
Angus King
Angus King
Representative
Chellie Pingree
Budget Funding
Federal Account | Budget Subfunction | Object Class | Total | Percentage |
---|---|---|---|---|
Shipbuilding and Conversion, Navy (017-1611) | Department of Defense-Military | Equipment (31.0) | $47,050,031 | 100% |
Modified: 4/23/25