GRAND ISLAND SUBSTATION, STAGE 08 AND SIOUX FALLS SUBSTATION, STAGE 15, STATION SERIVE UPGRADES, NEBRASKA AND SOUTH DAKOTA
Awardee
Awarding / Funding Agency
Place of Performance
Sioux Falls, SD 57104 United States
Pricing
Fixed Price
Set Aside
Small Business Set Aside - Total (SBA)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Related Opportunity
Addison Construction Co was awarded
Definitive Contract 89503425CWA000081 (895034-25-C-WA000081)
worth up to $2,337,721
by Western Area Power Administration
in September 2025.
The contract
has a duration of 1 year 8 months and
was awarded
through solicitation Grand Island Sioux Falls Substations Upgrades
with a Small Business Total set aside
with
NAICS 237130 and
PSC Y1PZ
via sealed bid acquisition procedures with 1 bid received.
Status
(Open)
Last Modified 9/10/25
Period of Performance
9/10/25
Start Date
5/31/27
Current End Date
5/31/27
Potential End Date
Obligations
$2.3M
Total Obligated
$2.3M
Current Award
$2.3M
Potential Award
Award Hierarchy
Definitive Contract
89503425CWA000081
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for 89503425CWA000081
People
Suggested agency contacts for 89503425CWA000081
Competition
Number of Bidders
1
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Awardee UEI
D4N8K3L9E824
Awardee CAGE
48738
Agency Detail
Awarding Office
895034 WESTERN-UPPER GREAT PLAINS REGION
Funding Office
895005
Created By
richter@wapa.gov
Last Modified By
richter@wapa.gov
Approved By
richter@wapa.gov
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
SD-00
Senators
John Thune
Mike Rounds
Mike Rounds
Representative
Dusty Johnson