TAINTER VALVE REHABILITATION
Awardee
Awarding / Funding Agency
Place of Performance
Stennis Space Center, MS 39529 United States
Pricing
Fixed Price
Set Aside
Hubzone Set-Aside (HZC)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Healtheon was awarded Delivery Order 80SSC025F7017 (80SSC0-25-F-7017) for Tainter Valve Rehabilitation worth up to $6,258,715 by Stennis Space Center in September 2025. The contract has a duration of 1 year 6 months and was awarded through solicitation 80SSC025R7003 with a Hubzone set aside with NAICS 236210 and PSC Z2KA via subject to multiple award fair opportunity acquisition procedures with 3 bids received. This contract was awarded through vehicle NSAS Regionalized Multiple Award Construction Contract II (MACC-II).

Status
(Open)

Last Modified 9/30/25
Period of Performance
9/30/25
Start Date
3/24/27
Current End Date
3/24/27
Potential End Date
0% Complete

Obligations
$6.3M
Total Obligated
$6.3M
Current Award
$6.3M
Potential Award
100% Funded

Award Hierarchy

Indefinite Delivery Contract

80SSC018D0005

Delivery Order

80SSC018D0005-80SSC025F7017

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to 80SSC018D0005-80SSC025F7017

People

Suggested agency contacts for 80SSC018D0005-80SSC025F7017

Competition

Number of Bidders
3
Solicitation Procedures
Subject To Multiple Award Fair Opportunity
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Awardee UEI
YNMQH3WNRBN5
Awardee CAGE
1YTH1
Agency Detail
Awarding Office
80SSC0 NASA STENNIS SPACE CENTER
Funding Office
80SSC0
Created By
andrew.m.franklin@nasa.gov
Last Modified By
andrew.m.franklin@nasa.gov
Approved By
andrew.m.franklin@nasa.gov

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
MS-04
Senators
Roger Wicker
Cindy Hyde-Smith
Representative
Walter Ezell
Modified: 9/30/25