80KSC019C0013

Definitive Contract

Overview

Government Description
Design and construction of the NASA Space Launch System (SLS) Mobile Launcher 2 (ML2) includes engineering design services, fabrication and installation of structural and miscellaneous steel, module fabrication, assembly of enclosures, installation of HVAC and cooling systems, electrical supply and raceway components, piping and fittings, launch equipment, and qualification testing. Additional tasks involve technical services support, stormwater system design, fire detection and alarm design services, and provision of construction equipment, temporary buildings, and site development. The work also encompasses assembly and installation of electrical and communication equipment, panel assemblies, cable management, weather instruments, painting and coatings, metrology and Non-Destructive Examination (NDE) services, crane and forklift operations, fabrication and transport of steel plates and pipe supports, and technical services in support of connection and vehicle stabilizer design. Further activities include module fabrication, construction elevator installation, HVAC maintenance, chemical cleaning design services, and third-party testing.
Awarding / Funding Agency
Place of Performance
Reston, VA 20190 United States
Pricing
Cost Plus Award Fee
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 02/28/23 to 06/05/26 and the Potential Award value has increased 12% from $1,410,175,214 to $1,583,975,214.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The National Aeronautics and Space Administration has an overall small business subcontracting goal of 34%
Bechtel National was awarded Definitive Contract 80KSC019C0013 (80KSC0-19-C-0013) for Design And Construction Of NASA Space Launch System (SLS) Mobile Launcher 2 (ML2) worth up to $1,583,975,214 by Kennedy Space Center in July 2019. The contract has a duration of 7 years and was awarded through solicitation Mobile Launcher 2 (ML2) full & open with NAICS 236210 and PSC AR15 via two step acquisition procedures with 3 bids received. As of today, the Definitive Contract has a total reported backlog of $33,285,860 and funded backlog of $33,285,860.

Status
(Open)

Last Modified 3/2/26
Period of Performance
7/1/19
Start Date
6/5/26
Current End Date
6/5/26
Potential End Date
98.0% Complete

Obligations and Backlog
$1.6B
Total Obligated
$1.6B
Current Award
$1.6B
Potential Award
98% Funded
$33.3M
Funded Backlog
$33.3M
Total Backlog

Award Hierarchy

Definitive Contract

80KSC019C0013

Subcontracts

-

Activity Timeline

Interactive chart of timeline of amendments to 80KSC019C0013

Labor Services Billing

Annual labor billing rates and FTE reported for 80KSC019C0013

Subcontract Awards

Disclosed subcontracts for 80KSC019C0013

Opportunity Lifecycle

Procurement history for 80KSC019C0013

Transaction History

Modifications to 80KSC019C0013

People

Suggested agency contacts for 80KSC019C0013

Competition

Number of Bidders
3
Solicitation Procedures
Two Step
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Yes
Business Size Determination
Large Business
Awardee UEI
WA9LNGN2DPF4
Awardee CAGE
324H5
Agency Detail
Awarding Office
80KSC0 NASA KENNEDY SPACE CENTER
Funding Office
80KSC0
Created By
jerry.r.kalka@nasa.gov
Last Modified By
jerry.r.kalka@nasa.gov
Approved By
jerry.r.kalka@nasa.gov

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
VA-11
Senators
Mark Warner
Timothy Kaine
Representative
Gerald Connolly

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Exploration, National Aeronautics and Space Administration (080-0124) Space flight, research, and supporting activities Land and structures (32.0) $686,919,036 100%
Modified: 3/2/26