Funds construction project MT flap bor 2980(1), sun river bridge replacement. Project includes construction of a 3 span, 462-FOOT long precast-post-tensioned girder bridge with a precast concrete deck. The work involves building a new bridge approximately 200 feet downstream from the existing bridge, with new approach roadways on embankments and Mechanically Stabilized Earth (MSE) wall approaches. Abutments are founded on both spread footings and piles within an MSE wall fill, piers are supported on 10-FOOT diameter drilled shafts, and final surfacing consists of gravel for the approaches and concrete on the bridge; the work may also include demolition of the existing steel truss bridge upon completion of the new structure.
Awardee
Awarding / Funding Agency
Place of Performance
Augusta, MT 59410 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Amendment Since initial award the Potential Award value has increased 3% from $16,391,289 to $16,904,108.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Transportation has an overall small business subcontracting goal of 43%
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Transportation has an overall small business subcontracting goal of 43%
Hamilton Construction Co was awarded
Definitive Contract 69056725C000006 (690567-25-C-000006)
for Sun River Bridge Replacement (MT FLAP BOR 2980(1))
worth up to $16,904,108
by Western Federal Lands Highway Division
in January 2025.
The contract
has a duration of 1 year 9 months and
was awarded
through solicitation MT FLAP BOR 2980(1), Sun River Bridge Replacement
full & open
with
NAICS 237310 and
PSC Y1LB
via sealed bid acquisition procedures with 5 bids received.
Status
(Open)
Last Modified 3/11/26
Period of Performance
1/13/25
Start Date
10/31/26
Current End Date
10/31/26
Potential End Date
Obligations
$16.9M
Total Obligated
$16.9M
Current Award
$16.9M
Potential Award
Award Hierarchy
Definitive Contract
69056725C000006
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for 69056725C000006
Transaction History
Modifications to 69056725C000006
People
Suggested agency contacts for 69056725C000006
Competition
Number of Bidders
5
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Awardee UEI
EJDKU2KTJE61
Awardee CAGE
3EZE5
Agency Detail
Awarding Office
690567 690567 WESTERN FEDERAL LANDS DIV
Funding Office
690567
Created By
julie.green.ctr@dot.gov
Last Modified By
julie.green.ctr@dot.gov
Approved By
julie.green.ctr@dot.gov
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Labor Standards
Performance District
MT-02
Senators
Jon Tester
Steve Daines
Steve Daines
Representative
Matthew Rosendale