Search Prime Contracts

15BBNF26C00000033

Definitive Contract

Overview

Government Description
B&F Project 24Z4AT1-REPLACE Boilers & Controllers
Funding Agency
Place of Performance
Pekin, IL 61554 United States
Pricing
Fixed Price
Set Aside
Small Business Set Aside - Total (SBA)
Extent Competed
Full And Open Competition After Exclusion Of Sources
Voris Mechanical was awarded Definitive Contract 15BBNF26C00000033 (15BBNF-26-C-00000033) for B&F Project 24Z4At1-Replace Boilers & Controllers worth up to $1,164,300 by FCI Pekin in March 2026. The contract has a duration of 5 months and was awarded through solicitation FCI Pekin - Replace Boilers & Controls with a Small Business Total set aside with NAICS 238220 and PSC Z2FF via sealed bid acquisition procedures with 5 bids received.

Status
(Open)

Last Modified 3/5/26
Period of Performance
3/5/26
Start Date
7/8/26
Current End Date
8/8/26
Potential End Date
15.0% Complete

Obligations
$1.2M
Total Obligated
$1.2M
Current Award
$1.2M
Potential Award
100% Funded

Award Hierarchy

Definitive Contract

15BBNF26C00000033

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to 15BBNF26C00000033

Opportunity Lifecycle

Procurement history for 15BBNF26C00000033

People

Suggested agency contacts for 15BBNF26C00000033

Competition

Number of Bidders
5
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Plan Not Required
Cost Accounting Standards
Exempt
Business Size Determination
Small Business
Awardee UEI
N1QXZ9T1EJW6
Awardee CAGE
1TK64
Agency Detail
Awarding Office
15BBNF BUILDING AND FACILITIES (FAO)
Funding Office
15B411
Created By
kaslone
Last Modified By
kaslone
Approved By
kaslone

Legislative

Legislative Mandates
Construction Wage Rate Requirements
Performance District
IL-17
Senators
Richard Durbin
Tammy Duckworth
Representative
Eric Sorensen
Modified: 3/5/26