1305M426C0007

Definitive Contract

Overview

Government Description
The National Oceanic and Atmospheric Administration (NOAA) has a requirement for a campus addition construction project for the northwest fisheries science center (NWFSC) at the Manchester Research Station (MRS), 7305 beach drive east, manchester, WA. The project involves ground-up construction of approximately 24,000 GSF for a new, energy-efficient facility that will include modern laboratory spaces for data collection and research focused on marine species' life cycles and the impacts of ecosystem stressors. The facility will feature recirculating aquatic systems (fresh and saltwater), wet and dry labs, facility and freezer storage, gas generation, office spaces, hatcheries for ocean acidification and toxicology research, electrical, mechanical, and communication spaces, as well as site work such as utilities, sidewalks, parking, roadways, and landscaping. The project will also relocate necessary research functions from the montlake facility and the decommissioned mukilteo facility to MRS.
Place of Performance
Port Orchard, WA 98366 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Analysis Notes
Amendment Since initial award the Potential End Date has been extended from 06/01/28 to 06/12/28 and the Potential Award value has increased 2% from $48,579,544 to $49,579,544.
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Commerce has an overall small business subcontracting goal of 30%
Future Set Aside Approximately 99% of recent NAICS 236220 contracts awarded by NOAA are set aside even though this Definitive Contract was not, indicating a potential higher likelihood that future purchases may be set aside for a small business
Balfour Beatty Construction was awarded Definitive Contract 1305M426C0007 (1305M4-26-C-0007) for Manchester Research Station (MRS) Campus Addition Construction – NOAA/NWFSC worth up to $49,579,544 by National Oceanic and Atmospheric Administration in June 2026. The contract has a duration of 2 years and was awarded through solicitation Manchester Campus Addition Construction at the Manchester Research Station in Port Orchard, Washington full & open with NAICS 236220 and PSC Y1AZ via direct negotiation acquisition procedures with 5 bids received. As of today, the Definitive Contract has a total reported backlog of $16,409,113.

Status
(Open)

Last Modified 8/26/26
Period of Performance
6/1/26
Start Date
5/12/28
Current End Date
6/12/28
Potential End Date
12.0% Complete

Obligations and Backlog
$33.2M
Total Obligated
$33.2M
Current Award
$49.6M
Potential Award
67% Funded
$0.0
Funded Backlog
$16.4M
Total Backlog

Award Hierarchy

Definitive Contract

1305M426C0007

Subcontracts

0

Activity Timeline

Interactive chart of timeline of amendments to 1305M426C0007

Opportunity Lifecycle

Procurement history for 1305M426C0007

Transaction History

Modifications to 1305M426C0007

People

Suggested agency contacts for 1305M426C0007

Competition

Number of Bidders
5
Solicitation Procedures
Negotiated Proposal/Quote
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No

Other Categorizations

Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Awardee UEI
PLF5D1ZJDQ63
Awardee CAGE
1XMC0
Agency Detail
Awarding Office
1305M4 DEPT OF COMMERCE NOAA
Funding Office
1333BT
Created By
ronette.mcbean-felder@noaa.gov
Last Modified By
ronette.mcbean-felder@noaa.gov
Approved By
ronette.mcbean-felder@noaa.gov

Legislative

Legislative Mandates
Construction Wage Rate Requirements Labor Standards
Performance District
WA-06
Senators
Maria Cantwell
Patty Murray
Representative
Derek Kilmer
Modified: 8/26/26