Search Contract Opportunities

COLO 253093 York River Shoreline Stabilization 2B   4

ID: 140P2021R0066 • Type: Sources Sought

Description

COLO 253093 - York River Shoreline Stabilization Phase 2B, Colonial National Historical Park, Yorktown, Virginia. This project will stabilize and rehabilitate portions of the York River shoreline that have been severely eroded. The stability of Colonial Parkway is threatened without repairs to the steep embankments that are within 25-50 feet of the Parkway. The project is design-build and includes pre- and post- construction surveys of the project area, clearing and grubbing, repositioning of existing stone, placement of riprap stone to construct rock sills, breakwaters, and revetment structures, the placement of geotextile fabric, excavation and filling earthwork, steep slope stabilization with geotextile bags and steel sheet pile wall, planting on the geotextile bag slopes, wetland fill material placement, wetland planting, and any incidental work related to the construction of this project. The project encompasses a portion of the York River shoreline between Williamsburg and Yorktown, and includes two reaches of approximately 3.1 miles with a total period of performance of 540 days. Reach 1 extends from Felgates Creek on the west to Indian Field Creek on the east, a distance of about 1.7 miles. Reach 2 extends from the mouth of Indian Field Creek on the west to the west pier of the Yorktown Naval Weapons Station on the east, a distance of about 1.4 miles. The project shall improve shoreline erosion control, stability, and natural wetland habitat for decades to come. This is a sources sought announcement, not a formal solicitation. Please see the attachment for further information regarding how to respond to this sources sought announcement.
Background
The project is a design-build contract located at Colonial National Historical Park, Yorktown, Virginia. The project aims to stabilize and rehabilitate severely eroded portions of the York River shoreline, which threatens the stability of Colonial Parkway. The National Park Service (NPS) is conducting market research through this Sources Sought Notice to determine the type of interested businesses and their qualifications. The NPS anticipates issuing a request for proposals in the late winter/spring of 2021 and expects a period of performance of 540 calendar days.

Work Details
The project includes pre- and post-construction surveys, clearing and grubbing, repositioning of existing stone, placement of riprap stone to construct rock sills, breakwaters, and revetment structures, placement of geotextile fabric, excavation and filling earthwork, steep slope stabilization with geotextile bags and steel sheet pile wall, planting on the geotextile bag slopes, wetland fill material placement, wetland planting, and any incidental work related to the construction. The project encompasses a portion of the York River shoreline between Williamsburg and Yorktown and includes two reaches of approximately 3.1 miles with a total period of performance of 540 days.

Period of Performance
The anticipated period of performance is 540 calendar days including any potential weather shutdown. There are 'in water' work restrictions from Feb 15 – June 30 during the construction season.

Place of Performance
The project encompasses a portion of the York River shoreline between Williamsburg and Yorktown, Virginia.

Overview

Response Deadline
Feb. 15, 2021, 12:00 a.m. EST Past Due
Posted
Feb. 1, 2021, 9:50 a.m. EST
Set Aside
None
Place of Performance
P.O. Box 210, Yorktown, VA 23690-0210 United States
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Est. Level of Competition
Low
Odds of Award
63%
On 2/1/21 Denver Service Center issued Sources Sought 140P2021R0066 for COLO 253093 York River Shoreline Stabilization 2B due 2/15/21. The opportunity was issued full & open with NAICS 237990 and PSC Z1QA.
Primary Contact
Name
Braaten, Jennifer   Profile
Phone
None

Documents

Posted documents for Sources Sought 140P2021R0066

Question & Answer

Opportunity Lifecycle

Procurement notices related to Sources Sought 140P2021R0066

Award Notifications

Agency published notification of awards for Sources Sought 140P2021R0066

Contract Awards

Prime contracts awarded through Sources Sought 140P2021R0066

Incumbent or Similar Awards

Potential Bidders and Partners

Awardees that have won contracts similar to Sources Sought 140P2021R0066

Similar Active Opportunities

Open contract opportunities similar to Sources Sought 140P2021R0066

Additional Details

Source Agency Hierarchy
INTERIOR, DEPARTMENT OF THE > NATIONAL PARK SERVICE > DSC CONTRACTING SERVICES DIVISION
FPDS Organization Code
1443-20000
Source Organization Code
100173195
Last Updated
Sept. 30, 2021
Last Updated By
fbms_acq@ios.doi.gov
Archive Date
Sept. 30, 2021