Description

North Gunnison 115-kV Switch Installation to add a 115kV Disconnect Switch to the bus work to provide flexible operation to feed the North Gunnison loads and allow WAPA to maintain all the electrical substation equipment.
a. Provide demolition and site development.
b. Remove and dispose of existing pedestals, rigid bus, insulators, and concrete foundations.
c. Furnish and install 115kV disconnect switch, structural steel, foundations, and associated equipment.
Background
The North Gunnison Substation 115kV Switch Installation project is issued by the Western Area Power Administration (WAPA), a part of the U.S. Department of Energy. The mission of WAPA is to market and deliver reliable, cost-based hydroelectric power and related services to its customers. The goal of this contract is to enhance operational flexibility for feeding North Gunnison loads while allowing maintenance of electrical substation equipment.

Work Details
The contractor will perform the following tasks:

1. Demolition and site development, including the removal and disposal of existing pedestals, rigid bus, insulators, and concrete foundations.

2. Furnishing and installation of a 115kV disconnect switch, structural steel, foundations, and associated equipment.

The work includes mobilization and preparatory work (not to exceed 5% of total), miscellaneous sitework, concrete foundations (12 cubic yards), steel structures (2075 pounds), a three-phase disconnecting switch (138-kV, 2000-amps), and associated electrical equipment.

Period of Performance
The contractor shall begin performance within 10 calendar days after receiving the notice to proceed and complete it within 730 calendar days.

Place of Performance
The construction projects will be performed at the North Gunnison Substation in Colorado.

Bidder Requirements
Bidders must provide performance and payment bonds within 10 calendar days after award.
Loading Map
Loading Map

Overview

Response Deadline
July 6, 2026, 4:00 p.m. EDT Due in 19 Days
Posted
June 3, 2026, 2:11 p.m. EDT (updated: June 12, 2026, 4:44 p.m. EDT)
Set Aside
None
Place of Performance
Gunnison, CO USA
Source

Current SBA Size Standard
$45 Million
Est. Level of Competition
Average
Est. Value Range
$100,000 - $250,000 (value based on agency estimated range)
On 6/3/26 Department of Energy issued Solicitation 89503226BWA000078 for North Gunnison Substation 115kV Switch Install due 7/6/26. The opportunity was issued full & open with NAICS 237130 and PSC Y1PZ.
Primary Contact
Name
Pratt, John W.   Profile
Phone
(720) 962-7166

Documents

Posted documents for Solicitation 89503226BWA000078

Opportunity Assistant


AI Analysis

AI Generate

Opportunity Lifecycle

Procurement notices related to Solicitation 89503226BWA000078

Incumbent or Similar Awards

Contracts Similar to Solicitation 89503226BWA000078

Potential Bidders and Partners

Awardees that have won contracts similar to Solicitation 89503226BWA000078

Similar Active Opportunities

Open contract opportunities similar to Solicitation 89503226BWA000078

Experts for North Gunnison Substation 115kV Switch Install

Recommended subject matter experts available for hire

Additional Details

Source Agency Hierarchy
ENERGY, DEPARTMENT OF > ENERGY, DEPARTMENT OF > WESTERN-ROCKY MOUNTAIN REGION
FPDS Organization Code
8900-00067
Source Organization Code
100183457
Last Updated
June 12, 2026
Last Updated By
Stripes@hq.doe.gov
Archive Date
July 21, 2026