CONTRACT OPPORTUNITY

USDA SOUTH BUILDING, WASHINGTON DC, WING 6 & 7 DESIGN/BUILD MODERNIZATION   2

Type: Presolicitation • ID: 12314421R0006
HigherGov Subscribers Knew About this Opportunity Months Ago

Find opportunities months earlier with HigherGov Forecasts

Free Trial Schedule Demo

Description

  1. BACKGROUND

Built between 1930 and 1936 the United States Department of Agriculture (USDA)'s South Building is listed on the National Register of Historic Places. The Historic Preservation zones, at the basement and the first floor, require restoration. Most importantly, there are many life-safety issues which shall be addressed to comply with contemporary building codes, including accessibility guidelines. Additionally, there are environmental hazards, which require abatement. Modernization of the South Building Wing 6 and 7 will address these concerns; thereby, ensuring the safety of USDA employees and visitors.

The South Building is USDA's largest office building. The South Building encompasses approximately 2.2 million gross square feet occupying two (2) city blocks between Independence Avenue and C Street and 12th and 14th Streets, SW. There are six (6) main floors, a Sub-Basement (Ground Level), a Basement, and an Attic. The South Building has seven (7) wings, connected by a north building section called the Headhouse and a south building section called the Tailhouse. Clustered at the ends of each of the seven (7) north-south oriented wings are elevators, stairs, toilets, telecom and electrical closets. In between the wings are six (6) open courtyards for staff parking, excepting Court 4 which is for shipping and receiving. Courts 1, 2, and 3 have enclosed ramps which lead to the sub-basement level. The courtyards have side doors which allow access into or egress from the building wings. The building contains special spaces as the main cafeteria above Court 2, a 478-seat auditorium, a TV studio and a training center in Court 5, a major data center at Wing 4 basement, and a retail zone in the Wing 3 subbasement.

Approximately 33% of the South Building was modernized previously between 1998 and 2011. The Master Plan and the Modernization Concept Plans were completed circa 1995. The previous modernization phases were implemented through the design-bid-build process. Wing 3 modernization was completed in 2000, Wing 4 in 2003, the headhouse offices from Wing 3 through 5 in 2005, Mail Operations Center at Courtyard 4 in 2006, and Wing 5 in 2011. The design for the Tailhouse offices from Wing 3 through Wing 5 was completed in 2011; however, construction was not initiated due to insufficient funding.

The modernization of Wing 6 & 7 will be solicited and award in accordance with Two Phase Design-Build methods prescribed by FAR 36.3. The project will be executed through the Design-Build method utilizing a phased approach beginning with Wing 7 followed by Wing 6. Wing 7 design will commence after contract award. It is anticipated that Wing 6 design will not commence until after both Wing 7 design is completed and construction work has begun. Wing 6 design will be completed prior to completion of Wing 7 construction so that construction at Wing 6 can commence at that point.

The work of the Wing 6 & 7 Modernization Project includes, but is not limited to, the following design disciplines and their related building/ site/ utility systems:

1. Civil Engineering

2. Geotechnical Engineering

3. Landscape Architecture

4. Environmental/ HAZMAT Remediation Engineering

5. Life Safety Engineering

6. Architecture

7. Historic Preservation

8. Interior Design

9. Structural Engineering

10. Blast & ATFP Engineering

11. Mechanical and HVAC Engineering

12. Plumbing Engineering

13. Fire Detection and Suppression Engineering

14. Electrical Engineering

15. Information Technology Engineering

16. Telecommunications Engineering

17. Vertical Transportation Engineering

18. Sustainability

19. Commissioning (General & Enhanced)

The Wing 6 and 7 modernization shall be USGBC LEED Silver certified per LEED v4 IC+C, Commercial Interiors. Contractor and their Designers of Record shall develop their Sustainability approach to compliance and submit to Government for approval as part of their response to the Design-Build RFP.

The Wing 6 & 7 Modernization shall include select exterior building repairs and upgrades, updated interior finishes, plumbing fixtures/ risers/ laterals, energy efficient lighting systems, updated MEP and Fire Detection and Suppression systems, including Telecom and Data upgrades and infrastructure as required to support the increased population and correct existing deficiencies. Exterior building work is limited to the replacement and repair of roof systems, flashings, gutters, exterior masonry parapets repairs and sealant/ backer-rod replacement. Repainting and replacement of sealant around select existing exterior windows and doors, and at the interior surfaces of these exterior components. Perform exterior masonry repairs to mitigate water damage at select locations identified in the Design Documents. Exterior work includes replacement of retaining wall (moat wall) and adjacent landscaping. The South Building shall remain fully operational 24 hours per day, 7 days per week and 365 days per year.

2. Additional Details

  1. This is a Pre-solicitation notice, additional information will be provided when the full solicitation is published.
  2. The Request for Proposal (RFP) is scheduled to be published on or about June 01, 2021 on beta.SAM.gov.
  3. Phase 1 responses are scheduled for submission on or about June 15, 2021.
  4. Solicitation documents will be provided electronically at no charge.
  5. The Rough Order of Magnitude (ROM) of this project is between 80 and 120 Million dollars.
  6. This potential award is not anticipated to be restricted to small businesses based on the fact of the size standard for NAICS code 236220 of $ 39.5 Million.
  7. Contractors interested in this Solicitation shall be added to the Interested Vendors List.

Overview

Response Deadline
May 10, 2021, 2:00 p.m. EDT Past Due
Posted
April 26, 2021, 2:34 p.m. EDT
Set Aside
None
Place of Performance
Washington, DC 20250 United States
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Est. Level of Competition
Low
Odds of Award
55%
On 4/26/21 USDA Office of the Chief Financial Officer issued Presolicitation 12314421R0006 for USDA SOUTH BUILDING, WASHINGTON DC, WING 6 & 7 DESIGN/BUILD MODERNIZATION due 5/10/21. The opportunity was issued full & open with NAICS 236220 and PSC Z2AA.
Primary Contact
Name
Gerardo F. Rivera   Profile
Phone
None

Secondary Contact

Name
Todd J. Lennox   Profile
Phone
None

Documents

Posted documents for Presolicitation 12314421R0006

Opportunity Lifecycle

Procurement notices related to Presolicitation 12314421R0006

Contract Awards

Prime contracts awarded through Presolicitation 12314421R0006

Incumbent or Similar Awards

Potential Bidders and Partners

Awardees that have won contracts similar to Presolicitation 12314421R0006

Similar Active Opportunities

Open contract opportunities similar to Presolicitation 12314421R0006

Additional Details

Source Agency Hierarchy
AGRICULTURE, DEPARTMENT OF > USDA, DEPARTMENTAL ADMINISTRATION > USDA, OCP-POD-ACQ-MGMT-BRANCH-FTC
FPDS Organization Code
1205-3144
Source Organization Code
100181286
Last Updated
May 25, 2021
Last Updated By
gerardo.rivera@usda.gov
Archive Date
May 25, 2021