Search Contract Opportunities

Tule River/Success Lake Spillway Enlargement Phase 2 Solicitation   2

ID: W91238-21-B-0010 • Type: Solicitation

Description

Posted: July 16, 2021, 5:36 p.m. EDT

TULE RIVER / SUCCESS LAKE SPILLWAY ENLARGEMENT PHASE 2

****Amendnent 0001 extends proposal due date, updates site visit date, and confirms full and open competition.****

The Government anticipates issuing a Invitation for bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W9123821B0010 / Tule River Phase 2

Project Description: The project generally consists of constructing a 10 foot high 350 foot long curved reinforced concrete ogee weir across Success lake spillway and constructing side walls and downstream Apron. The work will include widening of the spillway, excavating the Ogee weir and Apron foundation and weir slope embedment using blasting and/or excavation, and installation of rock anchors.

Additional project improvements include construction of trench drains at the main dam left abutments, flood proofing of existing recreation facilities, and raising and relocation of existing wells and storage tanks. Rock slope protection will be added to Frazier Dike and other areas around the lake.

In accordance with DFARS 236.204(ii) the estimated magnitude of construction is expected to be between $25,000,000 to $100,000,000. This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction).

Product Service Code is Y1LC (Construction of Tunnels and Subsurface Structures).

The solicitation will proceed as a Full and Open and is estimated to be issued on or about 03 Jun 2021 with bids due tentatively on 08 Jul 2021. The IFB will be issued on the Government Point of Entry known as https://sam.gov and will establish a firm bid due date/time.

Site Visit scheduled:

When: Thursday, 17 Jun 2021

Time: 0900 1200 PST

Where: Tule River/Success Lake, 29330 Highway 190, Porterville, CA 93257

Please respond to POC NLT 1200 PST on Wednesday, 16 JUN 2021

Site Visit POC's:

Mr. Charlie Mauldin Operations Park Manager, 559-784-0215
Mr. Calvin Foster Southern Operations Branch Chief, 559-281-0684

  • Location 1: Meet at the USACE office parking lot
  • Location 2: Tule Spillway
  • Location 3: Stockpile area and haul road
  • Location 4: HWY 190 Recreation area
  • Location 5: Frazier Dike
  • All attendees to sign in at location 1 the USACE office parking lot.
  • All attendees to observe CDC COVID requirements including wearing masks if required by CDC or local government.
  • Please try to carpool to limit the number of vehicles during the visit. Vehicles with high ground clearance are recommended.
  • Location 2 and 3 as listed above are currently a construction zone and have no public access the only time prospective bidder can visit that area is during this site visit. Please bring proper safety gear including hard hats, vests, ear & eye protection and steel toe boots.
  • USACE staff will not be answering questions during the visit. All questions to be submitted in writing and will be responded to in writing through ProjNet via the solicitation.
  • Photography will not be permitted. Requested photos may be taken by authorized Government personnel and posted to SAM.gov.

BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via https://sam.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check https://sam.gov frequently for any changes to the interested vendors list and notice.

** FOR .PDF FILES OF (SITE VISIT LOCATION IMAGES, GDR APP - B AND GDR APP - F) PLEASE CONTACT THE POC: V. SIMPKINS FOR A DOD SAFE LINK THE FILES ARE TOO BIG FOR SAM.GOV **

Amendment 0005 issued 07/01/2021 updating the Bid Schedule

Posted: July 12, 2021, 6:34 p.m. EDT
Posted: July 9, 2021, 2:23 p.m. EDT
Posted: July 6, 2021, 11:52 a.m. EDT
Posted: July 2, 2021, 1:10 a.m. EDT
Posted: June 30, 2021, 11:26 a.m. EDT
Posted: June 22, 2021, 1:53 p.m. EDT
Posted: June 21, 2021, 2:46 p.m. EDT
Posted: June 4, 2021, 10:12 a.m. EDT
Posted: June 3, 2021, 5:04 p.m. EDT
Posted: June 3, 2021, 4:12 p.m. EDT
Posted: June 3, 2021, 3:37 p.m. EDT
Posted: May 27, 2021, 9:47 p.m. EDT

Overview

Response Deadline
July 16, 2021, 2:00 p.m. EDT (original: June 25, 2021, 11:00 a.m. EDT) Past Due
Posted
May 27, 2021, 9:47 p.m. EDT (updated: July 16, 2021, 5:36 p.m. EDT)
Set Aside
None
Place of Performance
Porterville, CA United States
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Fixed Price
Est. Level of Competition
Average
On 5/27/21 USACE Sacramento District issued Solicitation W91238-21-B-0010 for Tule River/Success Lake Spillway Enlargement Phase 2 Solicitation due 7/16/21. The opportunity was issued full & open with NAICS 237990 and PSC Y1LC.
Primary Contact
Name
Vernon Simpkins   Profile
Phone
None

Secondary Contact

Name
Rachel Kinney   Profile
Phone
None

Documents

Posted documents for Solicitation W91238-21-B-0010

Question & Answer

Opportunity Lifecycle

Procurement notices related to Solicitation W91238-21-B-0010

Award Notifications

Agency published notification of awards for Solicitation W91238-21-B-0010

Contract Awards

Prime contracts awarded through Solicitation W91238-21-B-0010

Protests

GAO protests filed for Solicitation W91238-21-B-0010

Incumbent or Similar Awards

Potential Bidders and Partners

Awardees that have won contracts similar to Solicitation W91238-21-B-0010

Similar Active Opportunities

Open contract opportunities similar to Solicitation W91238-21-B-0010

Additional Details

Source Agency Hierarchy
DEPT OF DEFENSE > DEPT OF THE ARMY > USACE > SPD > US ARMY ENGINEER DISTRICT SACRAMENT
FPDS Organization Code
2100-W91238
Source Organization Code
100221301
Last Updated
July 31, 2021
Last Updated By
vernon.simpkins@usace.army.mil
Archive Date
July 31, 2021