South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB)

ID: 191BWC24C0008P00012 • Type: Award Notice • Match:  90%
Opportunity Assistant

Hello! Please let me know your questions about this opportunity. I will answer based on the available opportunity documents.

Please sign-in to link federal registration and award history to assistant. Sign in to upload a capability statement or catalogue for your company

Analyze Opportunity
Loading

Description

The purpose of this modification is to incorporate additional construction packages and Phase 1 expansion work into the progressive design-build contract. The modification adds the following construction packages:

Early Work Package (EWP) 1C Replacement In Kind

Final Construction Price: $13,147,453

Scope includes:

  • Removal and replacement of existing roofs.
  • Replacement of process equipment and piping.
  • Replacement of electrical equipment.
  • Replacement of odor control media.
  • Installation of new window sealants.
  • Replacement of coiling doors.
  • Replacement of emergency showers and eyewashes.
  • Painting and coating of existing facilities.

Early Work Package (EWP) 3B Early Procurement

Final Construction Price: $25,693,528

Scope includes procurement of critical long-lead equipment, including:

  • Standby generators and associated switchgear.
  • Medium-voltage switchgear.
  • Positive displacement blowers.
  • Submersible solids-handling pumps.
  • Dewatering centrifuges.
  • Stainless steel slide gates.
  • Stop logs.

Early Work Package (EWP) 4 Major Concrete Structures

Final Construction Price: $37,468,188

Scope includes:

  • Construction of major concrete structures for new Headworks facilities.
  • Primary Sedimentation Tanks 6 and 7.
  • Storage Warehouse.
  • New influent and drainage infrastructure.
  • Associated piping, carpentry, architectural, mechanical, electrical, and support features.

Phase 1 Base Construction Expansion

Final Construction Price: $369,613,306

Scope includes:

  • New Headworks facility with integrated pump station.
  • Screening and grit removal systems.
  • Primary sedimentation expansion.
  • Centralized odor control facilities.
  • Waste activated sludge thickening and storage facilities.
  • Dewatering upgrades.
  • Lime storage/feed and truck loadout facilities.
  • Storage warehouse.
  • Chlorination storage facility.
  • Administrative building expansion.
  • Multiple electrical buildings.
  • New electrical service, generators, utility distribution systems, process piping, and site work.
  • Rehabilitation of existing activated sludge tanks and lime silos.
  • Engineering services during construction and procurement of the effluent meter and bypass piping.

Construction Allowances

The contract also increases CLIN 008 Construction Allowances by $9,804,886, increasing the allowance amount from $1,783,374 to $11,588,260 to address uncertain construction elements and field conditions associated with EWP-1C and Phase 1 construction activities. [191BWC24C0008 P00012 | PDF]

Period of Performance

The base construction period of performance has been revised to 1,643 calendar days (54 months) from issuance of the Base Construction Notice to Proceed (NTP). Construction closeout requirements remain unchanged and must be completed within 180 calendar days following construction completion.

Award Value

  • Previous Contract Value: $106,449,546
  • Modification Increase: $445,922,475
  • Revised Total Contract Value: $552,372,021

Overview

Awardee
PCL Construction Inc. dba PCL Construction Services
Award ID
191BWC24C0006P00001
Reported Award
$552,372,021
Award Date
Posted
Set Aside
None
Place of Performance
San Ysidro, CA 92173 United States
Source

Current SBA Size Standard
$45 Million
Pricing
Multiple Types Common
South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB) (191BWC24C0008P00012) was awarded to PCL Construction Inc. dba PCL Construction Services on 10/13/26 by International Boundary and Water Commission U.S.-Mexico.
Primary Contact
Name
Philip Johnson   Profile
Phone
None

Documents

Posted documents for Award Notice 191BWC24C0008P00012

Opportunity Assistant


Analyze Opportunity

Award Notifications

Agency published notification of awards for Award Notice 191BWC24C0008P00012

Similar Active Opportunities

Open contract opportunities similar to Award Notice 191BWC24C0008P00012

Experts for South Bay International Wastewater Treatment Plant (SBIWTP) Rehabilitation and Expansion Progressive Design-Build (PDB)

Recommended subject matter experts available for hire

Additional Details

Source Agency Hierarchy
INTERNATIONAL BOUNDARY AND WATER COMMISSION: US-MEXICO > INTERNATIONAL BOUNDARY AND WATER COMMISSION: US-MEXICO > INTERNAT BOUNDARY AND WATER COMM
FPDS Organization Code
19BM-199401
Source Organization Code
500025680
Last Updated
Last Updated By
philip.johnson@ibwc.gov
Archive Date