Philpott Dam Landslide Remediation Bassett, Virginia   3

ID: W912PM23B0024 • Type: Solicitation

Description

PHL Landslide Construction

The following is a brief description of the proposed scope of work.

  • Overburden (soil) Removal: Controlled stripping and removal of the overburden overlying bedrock along the face of the slope.
  • Overburden (soil) Regrading: Controlled stripping and regrading of the overburden along the eastern portion of the project area. The regrading and removal of excess overburden reduces the potential of slope failure in that area, preventing damage to the facilities and equipment located at the toe.
  • Scaling: Controlled rock scaling along the slope areas to remove loose and unstable rock blocks from the face. Scaling will reduce the likelihood that rockfalls will occur.
  • Concrete T-walls: Pre-cast concrete T-walls should be installed at the toe of the slope and cabled together to prevent rockfall debris from reaching the powerhouse, and hence protect existing structures.
  • Draped Mesh: A draped mesh should be installed along the face of the slope to prevent rockfall debris from reaching the powerhouse area, and hence to protect existing structures.
  • Catchment Fence: Steel cable and wire mesh catchment fence should be erected at the toe of the slope to prevent rockfall debris from reaching the transformer yard and switchgear building, and hence to protect existing structures.
  • Secant Pile Retaining Wall: Construction of a secant pile retaining wall to stabilize the upper access road during the stripping and grading of the overburden on the slope downstream of the right abutment of the dam.
  • Stormwater Detention Vault: Due to the area of disturbance and VADEQ regulations the construction of a detention vault is necessary to limit the increased runoff in the project area due to the stripping and regrading of the soil. In addition to the construction of a detention vault, several new stormwater pipes will be installed, and several other drop inlets and pipes will be replaced to handle the increased runoff on the stripped portion of the slope.
  • Miscellaneous Stormwater Feature Maintenance: To control and direct stormwater runoff to the detention vault and reduce the likelihood of water running along the upper access road (similar to what transpired during the 2020 slope failures), ditch maintenance and cleanout for the upper access road is incorporated into the design. Additionally, the replacement of an existing stormwater drop inlet, culvert and headwall to facilitate drainage away from the upper access road ditch is planned.
  • Construction of the Switchgear Building: The building which houses the switchgear equipment was destroyed by the landslide. Once built the new switchgear equipment will be put in place for reconnection of the powerhouse.
Background
The solicitation is for the Philpott Dam Landslide Remediation in Bassett, Virginia. The work involves slope stability remediation to reduce the risk of personnel injury and damage to infrastructure due to landslide activity at the Philpott Dam site near Bassett, Virginia. The contractor will be responsible for obtaining and maintaining necessary licenses and permits, complying with Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work, and for all damages to persons or property that occur as a result of the Contractor's fault or negligence.

Work Details
The scope of work includes various construction tasks such as overburden (soil) removal and regrading, controlled rock scaling along the slope areas, installation of concrete T-walls, draped mesh, catchment fence, secant pile retaining wall construction, stormwater detention vault construction, miscellaneous stormwater feature maintenance, and construction of the switchgear building.
Additionally, the work involves drilling in soil and rock, casing, cleaning and inspections of shafts, concrete forming, placement & curing, weep drains, walers, top finishing, parapet and miscellaneous details.
The contractor shall furnish all labor, equipment, transportation, and materials necessary to perform all work in strict accordance with the specifications.

Place of Performance
The geographic location for the performance of construction projects is at Philpott Dam site near Bassett, Virginia.

Overview

Response Deadline
Aug. 23, 2023, 2:00 p.m. EDT (original: Aug. 9, 2023, 2:00 p.m. EDT) Past Due
Posted
July 10, 2023, 3:35 p.m. EDT (updated: Aug. 24, 2023, 3:31 p.m. EDT)
Set Aside
None
Place of Performance
Bassett, VA 24055 United States
Source
SAM

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Est. Level of Competition
Average
On 7/10/23 USACE Wilmington District issued Solicitation W912PM23B0024 for Philpott Dam Landslide Remediation Bassett, Virginia due 8/23/23. The opportunity was issued full & open with NAICS 237990 and PSC Y1KA.
Primary Contact
Name
Troy Small   Profile
Phone
(910) 524-4650

Secondary Contact

Name
Edward Boddie   Profile
Phone
(910) 251-4804

Documents

Posted documents for Solicitation W912PM23B0024

Question & Answer

Opportunity Lifecycle

Procurement notices related to Solicitation W912PM23B0024

Award Notifications

Agency published notification of awards for Solicitation W912PM23B0024

Contract Awards

Prime contracts awarded through Solicitation W912PM23B0024

Incumbent or Similar Awards

Contracts Similar to Solicitation W912PM23B0024

Potential Bidders and Partners

Awardees that have won contracts similar to Solicitation W912PM23B0024

Similar Active Opportunities

Open contract opportunities similar to Solicitation W912PM23B0024

Additional Details

Source Agency Hierarchy
DEPT OF DEFENSE > DEPT OF THE ARMY > USACE > SAD > US ARMY ENGINEER DISTRICT WILMINGTO
FPDS Organization Code
2100-W912PM
Source Organization Code
500039400
Last Updated
Sept. 7, 2023
Last Updated By
troy.d.small@usace.army.mil
Archive Date
Sept. 7, 2023