Building 20602 Remodel DNWS Classroom

ID: W912PP21Q0066 • Type: Award Notice • Match:  100%
Opportunity Assistant

Hello! Please let me know your questions about this opportunity. I will answer based on the available opportunity documents.

Please sign-in to link federal registration and award history to assistant. Sign in to upload a capability statement or catalogue for your company

Some suggestions:
Please summarize the work to be completed under this opportunity
Does this contract have any security clearance requirements?
I'd like to anonymously submit a question to the procurement officer(s)
Loading

Description

1. GENERAL REQUIREMENTS:

1.1 The contractor shall furnish all parts, material, labor, equipment, and supervision

necessary to complete the remodel work for a DNWS classroom located at Building

20602. The work shall include the following requirements listed in the specific

requirements. The contractor shall assure the DD Form 1354 are completed within 3

working days of place in service date and submitted to Kirtland AFB Real Property

office to get it staffed to the BCE for signature, at the conclusion of the project.

Background: The current classroom is not large enough to support the number of students in each

course for the curriculum. DNWS is requesting to remodel the classroom and remove

the adjoining wall to enlarge the space for future use and growth of the existing

classroom.

SPECIFIC REQUIREMENTS:

2.1 Contractor shall remove two (2) cinder block walls between classroom (104B and

office (106B) up to the I-beam level in their entirety. All removal and disposal of

materials, and/or equipment shall be the responsibility of the Contractor with no

additional expense to the Government. All remaining edges and corners shall be

protected and flush with existing gypsum board for safety purposes.

2.2 Contractor shall install sheetrock on walls, using 3 studs Ga. 20 and 5/8 thick

gypsum board.

2.3 Contractor shall paint walls including primer and 2 coats of paint. All paints to be

used shall be submitted as part of the normal submittal procedure and approved by

the USACE Contracting Officer Representative.

2.4 Contractor shall install new suspended ceiling using a 2'x2' ceiling tile at the same

height than the existing ceiling. Quantity of ceiling tiles required as par to of this

project shall be verified at the site visit prior to bidding deadlines. The Contractor is

responsible for furnishing all ceiling tiles to provide a complete system both for

functionality and aesthetically to blend with surround ceiling surfaces.

2.5 Contractor shall replace lighting with New 2'x2'LED lighting fixtures with dimmer

and all associated wiring/switches for a complete and usable system.

2.6 Contractor shall replace lighting fixtures type can with LED Recessed can

Lighting with dimmer as indicated on the drawings and discussed at the site visit.

Final quantities shall be the responsibility of the Contractor at no additional expense

to the Government.

2.7 Contractor shall replace and paint new three (3) ea. solid core doors and hardware.

Colors of paint shall be submitted by the Contractor to the USACE COR for

approval prior to application of paint during the construction process. The existing

frames will not be replaced; however, the contractor will be required to paint these

frames in accordance with project specifications.

2.8 Contractor shall remove one double door and frame, and closed the existing opening

using same classroom proposed wall material and finishes. Install panic devices on

new doors.

2.9 The Contractor shall remove the existing floor carpet, patch, and install DTRA

provided carpet tiles. The carpet tiles provided by DTRA are considered GFCI

(Government Furnished Contractor Installed) for the purpose of the construction

contract. Carpet adhesives and all associated materials required to correctly install

carpet tiles per the manufacturer's recommendation shall be provided by the

Contractor at no additional expense to the Government.

2.10 Clean/shampoo carpet once project is complete utilizing an approved carpet cleaner

and applicator designed for carpet tile style areas.

2.11 The contractor shall replace the existing sprinkler escutcheon covers. Exact

quantity will be the responsibility of the Contractor at no additional expense to the

Government. These quantities can be verified during the site visit conducted prior to

bid submission.

2.12 The Contractor shall replace the existing HVAC ceiling diffusers/grills with

matching or equivalent grills to ensure adequate throw distance and flow rates into

the newly renovated area.

2.13 The Contractor shall remove all existing wall electrical devices, lighting switches,

receptacle outlets and any other existing infrastructure, and install new devices to

the new gypsum board walls at or near same location in compliance with code

height and distance between devices. Additional outlets might be needed following

code's minimum distance between the outlets, and these shall be provided by the

Contractor at no additional expense to the Government. The Contractor is

responsible for verifying any additional outlet locations, junction box requirements,

and ensure breaker capacity is adequate at the nearest panel box in accordance with

life safety and NEC requirements.

2.14 The Contractor shall eliminate utilities and drops not in service from the existing

walls device location pulling the cables back to the near J-box and terminated.

2.15 The existing column between the classrooms will remains. The contractor shall

cover the column perimeter with gypsum board wall panels and apply paint.

2.16 Relocate the existing screens and projectors from the existing walls to the renovated

walls. All mounting of screens, projectors, and any other electronic devices shall the

responsibility of the Contractor at no additional expense to the Government.

Fasteners, brackets, braces, etc. shall be supplied by the Contractor as part of this

construction contract.

2.17 Contractor shall install four (4) new drywalls to cover one of the long classroom

walls length and three (3) new drywalls at the other long classroom wall. These

locations will be identified and measurable during the site visit. Identifying

quantities shall be the responsibility of the Contractor and execution of this work

shall be at no additional expense to the Government.

2.18 The contractor shall provide raceways for the podium (data, power, signal). NIPR,

SVTC and SPR will be required at the podium. All electronic materials and/or

equipment shall comply with UFC, NEC, and contract specification requirements. If

discrepancies occur between the referenced literature the most stringent requirement

shall govern and is the responsibility of the Contractor at no additional expense to

the Government.

Overview

Awardee
G2I
Award ID
W912Pp21P0038
Reported Award
$249,260
Award Date
Aug. 25, 2021
Posted
Sept. 1, 2021, 1:33 p.m. EDT
Set Aside
8(a) Sole Source (8AN)
Place of Performance
Kirtland AFB, NM 87117 United States
Source

Current SBA Size Standard
$45 Million
Pricing
Likely Fixed Price
Signs of Shaping
70% of obligations for similar contracts within the Department of the Army were awarded full & open.
Building 20602 Remodel DNWS Classroom (W912PP21Q0066) was awarded to G2I on 9/1/21 by USACE Albuquerque District.
Primary Contact
Name
Glenda D. Kohlieber   Profile
Phone
(575) 652-4135

Documents

Posted documents for Award Notice W912PP21Q0066

Question & Answer

The AI Q&A Assistant has moved to the bottom right of the page

Award Notifications

Agency published notification of awards for Award Notice W912PP21Q0066

Contract Awards

Prime contracts awarded through Award Notice W912PP21Q0066

Similar Active Opportunities

Open contract opportunities similar to Award Notice W912PP21Q0066

Additional Details

Source Agency Hierarchy
DEPT OF DEFENSE > DEPT OF THE ARMY > USACE > SPD > W075 ENDIST ALBUQUERQUE
FPDS Organization Code
2100-W912PP
Source Organization Code
100221490
Last Updated
Sept. 9, 2021
Last Updated By
glenda.d.kohlieber@usace.army.mil
Archive Date
Sept. 9, 2021