UPGRADE OF BASEWIDE STORM WATER DRAINAGE SYSTEMS

Type: Forecast

Overview

Description
Several reports of flooded areas have been noted at multiple locations at NSA Souda Bay. According to the latest assessment report, certain drainage pipes are nearing their capacity to manage storm water. Consequently, the capacities of storm water systems, watercourses, and other drainage infrastructures may be exceeded on occasions. Effected areas throughout the base are B50, B93, B66, B97 and B43.Problem Description: B93 Flight-line elevation is higher than that of the pavement's, north of the building. At the building's main entrance there is no storm water pipes to help the area drain properly so storm water is cumulated creating ponds. Mission Impact: During storm events the water height might reach 15cm(6inch) making it difficult to enter the building without being wet. Proposed Solution: Install storm water drain pipes and divert water safely away from the building entrance. B66 Southeast corner Water is cumulated after storm events and is pooled next to the flight line B66 entrance door Water is cumulated outside the entrance door after rain events. B97 Swimming pool entrance Storm water is cumulated in front of the pool area. INCLUDES REPAIR ACTIONS RECOMMENDED BY T.O. N3319121F4427 FOR B214 ARGONAUT NORTH SIDE AREA. INCLUDES REPAIR ACTIONS RECOMMENDED BY T.O. N3319121F4427 FOR B214 ARGONAUT NORTH SIDE AREA. Problem Description: B43 Flight-line elevation is higher than that of the pavement's, north of the building. At the building's main entrance there is no storm water pipes to help the area drain properly so storm water is cumulated creating ponds. Mission Impact: During storm events the water height might reach 15cm(6inch) making it difficult to enter the building without being wet. Proposed Solution: Install storm water drain pipes and divert water safely away from t ... NOTE: description has been truncated, please see Project Note for full description.
Est. Value
Min: $2,000,000
Max: $7,500,000
Est. Award Date
Q2 2026
Source Est. Solicitation Date
Q2 2026
Set Aside
Small Business Set-Aside
Pricing
Fixed-Price
Procurement Method
Delivery Order/Task Order (not under Federal Supply Schedule Contract)
Forecast Type
New
Place of Performance
TBD, USA
Forecast Source
Naval Facilities Engineering Command
Naval Facilities Engineering Command is forecasted to issue a new procurement for UPGRADE OF BASEWIDE STORM WATER DRAINAGE SYSTEMS around Q2 2026 worth up to $7,500,000.

Agency

Source Level 1 Agency
Naval Facilities Engineering Command
Source Level 2 Agency
NAVFAC Europe Africa Central
Source Level 3 Agency
N62470

Contacts

Point of Contact
NAVFAC OSBP   Profile
Point of Contact Email

Potential Bidders and Partners

Similar Active Opportunities

Additional Detail

Date Published
6/12/25
Additional Notes
MAC - SB and RFP - BVSS (One Step)