There are three main transformers in the C-5 Substation that provide all of the power to the Launch Complex 39 area. This project replaces the second of the three transformers.
Est. Value
Min: $5,100,000
Max: $10,000,000
Max: $10,000,000
Est. Award Date
Q4 2026
Source Est. Solicitation Date
Q4 2026
Set Aside
Small Business Set Aside - Total
Pricing
Firm Fixed Price
Forecast Type
New Requirement
Place of Performance
FL USA
Forecast Source
National Aeronautics and Space Administration
Kennedy Space Center is forecasted to issue a new procurement for Replace C-5 Substation Primary Transformers, Phase 2 around Q4 2026 worth up to $10,000,000.
Agency
Source Level 1 Agency
National Aeronautics and Space Administration
Source Level 2 Agency
KSC
Contacts
Point of Contact
Sims, Tamara A.   Profile
Point of Contact Email
ksc-smallbusiness@mail.nasa.gov
SBA Advisor
ksc-smallbusiness@mail.nasa.gov
Small Business Offices
Potential Bidders and Partners
Similar Active Opportunities
Additional Detail
Date Published
9/18/25
Source Forecast ID
10110