This award obligates Section 5307 funds apportioned to UZA 1 in the amount of $240,814,132 for New York City Transit ($47,134,132) and LIRR ($193,680,000) projects. This award uses transportation development credits for match ($48,162,826). The toll credit approvals for appropriations through and including FFY 2022 is attached.

Purpose of the award - This award will assist the MTA to invest capital funding into its assets/infrastructure maintained by NYCT and LIRR.

Activities to be performed - The application scope of work includes new trackwork rehabilitation of existing right of way and ADA accessibility projects for NYCT and LIRR.

Expected outcomes - This application will support the MTA's need to rehabilitate and replace assets to achieve a state of good repair.

Intended beneficiaries - The MTA and its ridership.

Subrecipient activities - The MTA does not have subrecipients under this award.

The Section 5307 funds are from FY 2021-2022 allocations from the New York Metropolitan Transportation Council (NYMTC). A table is attached in TRAMS under application documents to show the amounts used by fiscal year and funding program (see file: MTA Funding Allocation Usage and Availability Grant 1786-2022-7).

1% security requirement - The MTA certifies that it will not expend 1% of the apportionment on security. The MTA utilizes local funds and awards from the Department of Homeland Security.

0.75% safety requirement - MTA's budget for 5307 funds is $240,814,132 in this grant. FTA requires at least $1,806,106 to be spent on safety-related projects. The MTA has identified Hall Interlocking Expansion L8030403 with a budget of $150,000,000 to satisfy this requirement.

This award includes the following projects:
P1 NYCT Track and Switch Rehabilitation SIR Mainline (Switches) SI02-8861 (S8070102) (TF 2021 FAST ACT)
P2 LIRR Hall Interlocking Expansion L8030403 (TF 2022 BIL)
P3 LIRR Mentor Allowance Shops Yards (HSF Loading Dock Exhaust HVAC) L70604YJ (TF 2022 BIL)
P4 LIRR ADA Station Renewal Locust Manor L8020411 (TF 2022 BIL)
P5 LIRR Amityville Copiague Lindenhurst and Massapequa Park New Elevators L8020413 (TF 2022 BIL)
P6 LIRR St Albans New Elevator (ADA) L8020414 (TF 2022 BIL)
P7 LIRR Hall Interlocking Expansion L8030403 (TF 2021 FAST ACT)
P8 LIRR Hall Interlocking Expansion L8030403 (TF 2022 BIL)
Awarding Agency
Place of Performance
New York United States
Geographic Scope
State-Wide
Related Opportunity
None
Analysis Notes
Infrastructure $179,780,482 (75%) percent this Project Grant was funded by the 2021 Infrastructure Act.
Metropolitan Transportation Authority was awarded Project Grant NY-2022-052 worth $240,814,132 from the FTA Office of Budget and Policy in September 2022 with work to be completed primarily in New York United States. The grant has a duration of 5 years 6 months and was awarded through assistance program 20.507 Federal Transit Formula Grants.

Status
(Ongoing)

Last Modified 9/19/22

Period of Performance
9/14/22
Start Date
3/31/28
End Date
28.0% Complete

Funding Split
$240.8M
Federal Obligation
$0.0
Non-Federal Obligation
$240.8M
Total Obligated
100.0% Federal Funding
0.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to NY-2022-052

Additional Detail

Award ID FAIN
NY-2022-052
SAI Number
NY-2022-052-00-20.507
Award ID URI
SAI EXEMPT
Awardee Classifications
Other
Awarding Office
692387 REGION 2 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
NXGWYMXLNW95
Awardee CAGE
4JQ71
Performance District
90
Senators
Kirsten Gillibrand
Charles Schumer

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Formula and Bus Grants, Liquidation of Contract Authorization, Federal Transit Administration, Transportation (069-8350) Ground transportation Grants, subsidies, and contributions (41.0) $240,814,132 100%
Modified: 9/19/22