This award obligates Section 5307 funds apportioned to UZA 1 in the amount of $235,548,713 for New York City Transit ($235,548,713) projects. This award uses $47,109,743 in transportation development credits for match. The toll credit approval for appropriations through and including FFY 2022 is attached.

Purpose of the award - This award assists the MTA to invest capital funding into its assets/infrastructure maintained by NYCT.

Activities to be performed - The application scope of work includes elevator replacement and substation rehabilitation projects for NYCT.

Expected outcomes - This application supports the MTA's need to rehabilitate and replace assets to achieve a state of good repair.

Intended beneficiaries - The MTA and its ridership.

Subrecipient activities - The MTA does not have subrecipients under this award. The Section 5307 funds will be from FY 2021 allocations from the New York Metropolitan Transportation Council (NYMTC). The regional sub-allocation resolution #544 is attached in TRAMS. A table is attached in TRAMS under application documents to show the amounts used by fiscal year and funding program (see file: MTA Funding Allocation Usage Available Funding_1786-2022-9).

The MTA requests that the FTA obligate the required funds for this application from the available fund balance.

1% security requirement - The MTA certifies that it will not expend 1% of the apportionment on security. The MTA utilizes local funds and awards from the Department of Homeland Security.

0.75% safety requirement - MTA's budget for 5307 funds is $235,548,713 in this award. FTA requires at least $1,766,615 to be spent on safety-related projects. The MTA has identified T8090202 Replace High Tension Switchgear at 6 Substations with a budget of $49,043,914 to satisfy this requirement.

This award includes the following projects:

P1 NYCT Replace 19 Elevators Various Locations MW48-8677 (T8040702) (2021 TF)

P2 NYCT Replace DC Lineup at Jamaica Yard Substation PW03-6236 (T8090202) (2021 TF)

P3 NYCT Replace High Tension Switchgear at 6 Substations PW03-6546 (T8090202) (2021 TF)
Awarding Agency
Place of Performance
New York United States
Geographic Scope
State-Wide
Related Opportunity
None
Metropolitan Transportation Authority was awarded Project Grant NY-2022-049 worth $235,548,713 from the FTA Office of Budget and Policy in September 2022 with work to be completed primarily in New York United States. The grant has a duration of 4 years 9 months and was awarded through assistance program 20.507 Federal Transit Formula Grants.

Status
(Ongoing)

Last Modified 9/19/22

Period of Performance
9/13/22
Start Date
6/30/27
End Date
32.0% Complete

Funding Split
$235.5M
Federal Obligation
$0.0
Non-Federal Obligation
$235.5M
Total Obligated
100.0% Federal Funding
0.0% Non-Federal Funding

Activity Timeline

Interactive chart of timeline of amendments to NY-2022-049

Additional Detail

Award ID FAIN
NY-2022-049
SAI Number
NY-2022-049-00-20.507
Award ID URI
SAI EXEMPT
Awardee Classifications
Other
Awarding Office
692387 REGION 2 DOT FTA
Funding Office
693JJ8 OFFICE OF BUDGET AND POLICY(TBP)
Awardee UEI
NXGWYMXLNW95
Awardee CAGE
4JQ71
Performance District
90
Senators
Kirsten Gillibrand
Charles Schumer

Budget Funding

Federal Account Budget Subfunction Object Class Total Percentage
Formula and Bus Grants, Liquidation of Contract Authorization, Federal Transit Administration, Transportation (069-8350) Ground transportation Grants, subsidies, and contributions (41.0) $235,548,713 100%
Modified: 9/19/22