W912P825CA008
Definitive Contract
Overview
Government Description
Mississippi river baton rouge to gulf, saltwater barrier sill, cutterhead dredge contract #1-25. The contractor will utilize a dredge and attendant plant to construct and potentially maintain a saltwater barrier sill between mile 63.0 and mile 64.0 Above Head Of Passes (AHP) on the Mississippi river by placing hydraulically dredged material from a designated borrow area. The project includes constructing the sill to specified dimensions, performing daily safety inspections, submitting an accident prevention plan with required safety forms, developing a dive plan for diving operations, erecting and maintaining safety and project signs, and implementing emergency alarms and signaling systems on floating plants used during construction.
Awardee
Awarding / Funding Agency
Place of Performance
New Orleans, LA 70118 United States
Pricing
Fixed Price
Set Aside
None
Extent Competed
Full And Open Competition
Related Opportunity
Analysis Notes
Subcontracting Plan This Definitive Contract has an Individual Subcontract Plan. The Department of Defense has an overall small business subcontracting goal of 30%
Weeks Marine was awarded
Definitive Contract W912P825CA008 (W912P8-25-C-A008)
for Emergency Construction of Saltwater Barrier Sill on Mississippi River
worth up to $31,460,000
by USACE New Orleans District
in September 2025.
The contract
has a duration of 8 months and
was awarded
through solicitation Mississippi River, Baton Rouge to the Gulf, Saltwater Barrier Sill, Cutterhead Dredge Contract No. 1-2025. Specification No. OM25135
full & open
with
NAICS 237990 and
PSC Y1KF
via sealed bid acquisition procedures with 1 bid received.
As of today, the Definitive Contract has a total reported backlog of $17,147,100.
DOD Announcements
Sep 2025:
Weeks Marine Inc., Covington, Louisiana, was awarded a $10,692,500 firm-fixed-price contract for emergency construction of a saltwater barrier sill on the Mississippi River. The total cumulative face value is $31,460,000. Work will be performed in Venice, Louisiana, with an estimated completion date of Oct. 27, 2025. Fiscal 2025 civil operation and maintenance, funds in the amount of $10,692,500 were obligated at the time of the award. U.S. Army Corps of Engineers, New Orleans District, is the contracting activity (W912P8-25-C-A008). (Awarded Sept. 22, 2025)
Status
(Open)
Last Modified 12/3/25
Period of Performance
9/24/25
Start Date
12/12/25
Current End Date
5/3/26
Potential End Date
Obligations and Backlog
$14.3M
Total Obligated
$14.3M
Current Award
$31.5M
Potential Award
$0.0
Funded Backlog
$17.1M
Total Backlog
Award Hierarchy
Definitive Contract
W912P825CA008
Subcontracts
Activity Timeline
Opportunity Lifecycle
Procurement history for W912P825CA008
Transaction History
Modifications to W912P825CA008
People
Suggested agency contacts for W912P825CA008
Competition
Number of Bidders
1
Solicitation Procedures
Sealed Bid
Evaluated Preference
None
Commercial Item Acquisition
Commercial Item Procedures Not Used
Simplified Procedures for Commercial Items
No
Other Categorizations
Subcontracting Plan
Individual Subcontract Plan
Cost Accounting Standards
Exempt
Business Size Determination
Large Business
Defense Program
None
DoD Claimant Code
None
IT Commercial Item Category
Not Applicable
Awardee UEI
ED3FZHBD52V3
Awardee CAGE
1RHV3
Agency Detail
Awarding Office
W912P8 W07V ENDIST NEW ORLEANS
Funding Office
W42HEM
Created By
shaun.a.mcafee@acws
Last Modified By
jeffery.waguespack.w912p8@sa2100.army.mil
Approved By
shaun.a.mcafee@acws
Legislative
Legislative Mandates
Construction Wage Rate Requirements
Performance District
LA-01
Senators
Bill Cassidy
John Kennedy
John Kennedy
Representative
Steve Scalise
Modified: 12/3/25