Carlson spit is eroding away and is in danger of affecting stability of Carderock pier and Port operations is losing storage space for oil booms. Was part of Boat Ramp project, but because of environmental approvals required by this project, it was split away from the boat ramp project.; Status Note (as of 26-MAY-21): WIB - To be discussed at the 6/3/21 WIB meeting.; Status Note (as of 27-MAY-21): To be assigned.; Status Note (as of 03-JUN-21): To be assigned.; Status Note (as of 26-MAY-21): WIB - To be discussed at the 6/3/21 WIB meeting.
Requires SAR ep #1701650 & 1391 ep #1701647, notified Molly Clendenin.; Status Note (as of 10-JUN-21): To be assigned.; Status Note (as of 17-JUN-21): SUMMARY: SAES being prepared.//COSTS: Nothing significant to report.//SCHED: Design pre-award on schedule.//ENV: N/A.//OTHER: N/A.; Status Note (as of 24-JUN-21): To be assigned.; Status Note (as of 29-JUN-21): To be assigned.; Status Note (as of 08-JUL-21): To be assigned.; Status Note (as of 15-JUL-21): SUMMARY: SAES being prepared.//COSTS: Nothing significant to report.//SCHED: Design pre-award on schedule.//ENV: N/A.//OTHER: N/A.; Status Note (as of 22-JUL-21): To be assigned.; Status Note (as of 04-AUG-21): To be assigned.; Status Note (as of 12-AUG-21): To be assigned.; Status Note (as of 19-AUG-21): SUMMARY: To be assigned.//COSTS: N/A.//SCHED: N/A.//ENV: N/A.//OTHER: N/A.; Status Note (as of 26-AUG-21): To be assigned.; Status Note (as of 31-AUG-21): To be assigned.; Status Note (as of 10-SEP-21): To be assigned.; Status Note (as of 14-SEP-21): Assigned to Richard Goins.; Status Note (as of 14-SEP-21): Assigned to Richard Goins. FY22 Design/FY23 Construction.; Status Note (as of 16-SEP-21): SUMMARY: SAES being prepared.//COSTS: Nothing significant to report.//SCHED: Design pre-award on schedule.//ENV: N/A.//OTHER: N/A.; St ...
NOTE: description has been truncated, please see Project Note for full description.
Est. Value
Min: $2,000,000
Max: $7,500,000
Max: $7,500,000
Est. Award Date
Q3 2026
Source Est. Solicitation Date
Q3 2027
Set Aside
TBD
Pricing
Fixed-Price
Procurement Method
Delivery Order/Task Order (not under Federal Supply Schedule Contract)
Forecast Type
New
Place of Performance
USA
Forecast Source
Naval Facilities Engineering Command
NAVFAC Northwest is forecasted to issue a new procurement for Repair Eroded Shore line at Carlson Spit B7130, Bangor (20358245) (DB-IH) around Q3 2026 worth up to $7,500,000.
Agency
Source Level 1 Agency
Naval Facilities Engineering Command
Source Level 2 Agency
NAVFAC Northwest
Source Level 3 Agency
N44225
Contacts
Potential Bidders and Partners
Similar Active Opportunities
Additional Detail
Date Published
12/22/25
Additional Notes
MAC - General and RFP - BVSS (One Step)