Project Title: Replace 150A hot water lines at three locations in IKEGO.
1) Desired Completion Date:
3) Fund Source: CNIC ST
4) Supported Customer: Housing/Ikego
5) When funds will be available (If Customer Fund): FY25
6) Work Priority: Normal
7) Plant Replacement Value (PRV): N/A
1. Scope of Work:
a. Remove and excavate asphalt pavement and ground soil.
b. Remove existing 150A & 80A hot water lines with consumed Mg
anodes for Cathodic Protection (CP).
c. Provide new 150A & 80A hot water lines with new Mg anodes for CP.
d. New connecting point (NCP) is the inside of valve in pit (i.e. replace
valves also).
e. Perform leak test of new hot water lines.
f. Restore soil, grass and asphalt pavement.
2. Justification / Reason:
a. The casing piping is deteriorated and leaking.
3. Recommendation / Information / Special Requirements:
a. ST Project.
Est. Value
Min: $7,500,000
Max: $50,000,000
Max: $50,000,000
Est. Award Date
Q3 2026
Source Est. Solicitation Date
Q3 2025
Set Aside
TBD
Pricing
Fixed-Price
Procurement Method
Delivery Order/Task Order (not under Federal Supply Schedule Contract)
Forecast Type
New
Place of Performance
USA
Forecast Source
Naval Facilities Engineering Command
NAVFAC Far East is forecasted to issue a new procurement for E2 (UEM) IKE-HT-MAIN, REPLACE HOT WATER LINES around Q3 2026 worth up to $50,000,000.
Agency
Source Level 1 Agency
Naval Facilities Engineering Command
Source Level 2 Agency
NAVFAC Far East
Source Level 3 Agency
N40084
Contacts
Potential Bidders and Partners
Similar Active Opportunities
Additional Detail
Date Published
12/22/25
Additional Notes
MAC - General and RFP - BVSS (One Step)